Is Off Plan Property Safe in Dubai? Escrow, RERA and Oqood Explained

Is off plan safe in Dubai? Yes, when you check the right things. Learn how escrow, RERA and Oqood protect you, plus 7 checks and what to do if handover is late.

· 7 min read

Last updated: 6 November 2026.

The short answer

Off plan property in Dubai is regulated, and the law protects your money. Every payment must go into a project escrow account, and the developer can only take money out as construction moves forward. But the law does not promise an on time handover, perfect quality or good rent. It protects you only if you pay the right account and check the paperwork first.

Why this question matters

Most people don't fear the building. They fear paying a big deposit and then seeing the project stop, slip or disappear. That fear is fair. The good news is that Dubai built a system for exactly this problem, and you can check most of it yourself in an afternoon.

This guide covers Dubai. Abu Dhabi has its own rules, so check them separately if you are buying there.

The four protections, in plain words

1. Project registration

A developer must register a project with the Dubai Land Department, also called DLD, before it signs contracts or takes payments. The project gets a registration number, and adverts need a RERA permit number too. RERA is the DLD's regulator for the property market. If a seller can't show you a registration number, stop.

2. The escrow account

Escrow is a special bank account for one project. Under Dubai's Law No. 8 of 2007, every payment from buyers goes into it, and the developer can't use it for other projects or company costs. A law firm guide adds that developers must also put in money or a bank guarantee equal to 20% of the building cost before they start selling.

3. Oqood

This is the DLD's record of your off plan purchase. It ties your name to your exact unit, so nobody can sell the same unit twice. Your contract should be registered on Oqood soon after you sign. Treat anyone who says "we will do it later" as a warning sign.

4. Your contract

The Sales and Purchase Agreement, or SPA, sets your price, payment dates, handover date and what happens if something goes wrong. It is the paper you will rely on in a dispute, so read it before you pay.

How escrow works

Think of it as a locked box that opens in steps.

  1. You pay into the project's escrow account, never to the developer's own account.

  2. The developer builds a stage.

  3. An independent engineer checks the work and signs a certificate.

  4. RERA approves the certificate, and the bank releases the money for that stage.

  5. The bank keeps back 5% for about a year after handover, which acts as a guarantee for defects.

If a project fails, the money left in escrow does not belong to the developer. If RERA cancels the project, buyers can get refunds from the remaining funds, or another developer can take over and finish it.

What escrow does not protect

This is the part most guides skip.

  • Money paid outside escrow. If you pay an "admin fee" or "booking fee" to any other account, escrow does not cover it.

  • The handover date. Escrow protects your payments, not your schedule.

  • Rent and resale value. No law guarantees you will earn rent or sell for more.

  • Quality. Escrow does not guarantee finishing, though the 5% retention helps after handover.

Seven checks before you pay

  1. Check the developer. Search the developer's name in the Dubai REST app or on the DLD website. If it does not appear, it is not registered.

  2. Check the project. Ask for the project registration number, and confirm the developer on the record matches the company selling to you.

  3. Check the agent. Ask for the agent's Broker Registration Number, also called a BRN, and confirm it is current.

  4. Check the escrow account. Get the bank name and account number, and confirm them with the DLD and the bank. The account must belong to your project.

  5. Check the track record. Look at the developer's finished buildings. A developer with no completed projects is a bigger risk, so ask for the construction schedule.

  6. Read the contract. Look at the unit number, price, payment dates, handover date, late handover penalty and cancellation terms. A UAE real estate lawyer can review it for you.

  7. Get the numbers in writing. Ask for the price list, payment schedule, fees and VAT if you are buying a commercial unit.

Red flags

  • no project registration number

  • a payment request to a personal or company account instead of escrow

  • an agent with no BRN

  • adverts with no permit number

  • fixed or promised returns

  • cash or crypto payments

  • pressure to pay today

  • a seller who will not let you take the contract to a lawyer

  • no sales office or show unit

Common scams use these signs. Fake agents on social media collect deposits into private accounts, and some send forged documents or give bank details that lead away from escrow.

What happens if handover is late?

A small delay is normal and not always a breach. Many contracts allow an extra 6 to 12 months beyond the stated date, so check yours. After that, your options depend on the contract and the facts.

  1. Write to the developer. Ask for the reason and a new date, and keep the reply.

  2. Check the project status. Look it up on the DLD website or the Dubai REST app.

  3. Complain to the DLD. It can try to settle the dispute, and any agreement it approves is binding.

  4. Go to court. If mediation fails, you can file a civil case for compensation, which follows your contract or a judge's decision.

If a developer blames "force majeure," it has to prove an event outside its control caused the delay. Poor planning or money problems do not count, according to one law firm guide. If RERA cancels a project, a special tribunal handles refund claims.

Keep every document: the signed contract, payment receipts, your Oqood record, emails and screenshots of status checks.

What if you want to cancel?

Cancelling costs money. If you walk away without the developer's fault, the law lets the developer keep part of what you paid, and the amount depends on how far construction has reached. Sources give different percentages, so ask a lawyer for the exact figure before you sign.

Two examples from live launches

A joint launch. Berkeley Tower was announced by Ellington Properties and Al Hamra Group, and neither company has said what each does. On a project like that, ask which company signs your contract and which one holds the escrow account. You can see the project on our Berkeley Tower page.

A date that changes by source. On our Azizi Venice page, handover is listed for March 2027, while other sources give late 2026 for the first buildings. Dates differ by phase and source, so confirm the date for your exact building in your contract.

Is off plan right for you?

It may suit you if:

  • you can pay on the schedule without stress

  • you can wait through a delay of up to a year

  • you will check the paperwork before you pay

It may not suit you if:

  • you need to move in by a fixed date

  • you rely on rent starting on time

  • you feel pushed to decide quickly

Want help checking a project?

Tell us which project you like, and we will help you gather the registration number, escrow details, payment schedule and handover date to confirm with the developer. We are an information site, not the developer or a law firm, so we show you what to check. Use the form on this page or message us on WhatsApp.

This article is general information, not legal advice. Rules can change, so confirm details with the DLD or a qualified lawyer before you buy.

Sources: Kayrouz and Associates on developer obligations (March 2026), EGSH on escrow accounts (September 2026), EGSH on off plan delays, Real Estate Club Dubai on verifying developers, and Khaleej Times legal column on delays (June 2025).

Is off plan safe in Dubai?
It is regulated and your payments are protected by escrow, but you must check the registration, escrow account and contract yourself. It does not protect you from delays or a weak market.
What is an escrow account?
It is a bank account for one project. Buyer payments go in, and the developer takes money out only as construction reaches checked stages.
What is Oqood?
It is the DLD's record of your off plan purchase. It links your name to your unit and helps prevent double selling.
How do I check a developer in Dubai?
Search for the developer and project in the Dubai REST app or on the DLD website, and ask for the project registration number.
Can I lose my money in off plan?
You can if you pay outside escrow, buy from an unregistered seller or cancel after you sign. Paying into the verified escrow account protects you much more.
What happens if a developer goes bankrupt or stops building?
If RERA cancels the project, buyers can get refunds from the escrow funds, or another developer can finish it.
How long can a handover be delayed?
Many contracts allow 6 to 12 months of extra time. Check your contract for the exact period and any penalty.
Do I need a lawyer?
It is a good idea to have a UAE real estate lawyer review the contract, because it is the document you rely on in a dispute.

Share

General information only, not financial advice. Property values and rental income can fall as well as rise, and past performance is no guide to the future.

Register your interest

Clear advice, approved details

Tell us what you are looking for. An advisor will send a shortlist with current availability, floor plans and payment plans.

+971 52 341 7272admin@offplan.aeWhatsApp

Send me the details

Which best describes you?

We may contact you about this enquiry using the details you enter, even if you do not press send.